Holiday period opening hours
Over the holiday season, some of our facilities will be closed or have reduced hours.
Find out about the subdivision process if you are planning to divide land or buildings for separate ownership.
Subdivision is the process of dividing land or buildings for separate ownership. It can be a complex process and it is likely that you will need to seek advice – as well as engage the services – of professionals including a surveyor, accountant, solicitor, real estate agent, architect, valuer and a suitably qualified engineer.
One of the first things you will need to do if you are thinking about subdividing a property is to investigate the subdivision rules in the New Plymouth District Plan.
These rules relate to such things as:
The minimum allotment sizes that you may create through subdivision depend on which environment area the property is located in.
Environment area |
Controlled activity |
Discretionary activity |
---|---|---|
Residential A |
450m2 |
400m2 |
Residential B |
300m2 |
250m2 |
Residential C |
700m2 |
650m2 |
Business A, B and C |
No minimum |
n/a |
Business D |
300m2 |
250m2 |
Open space A |
500m2 |
400m2 |
Open space B and C, or Port Taranaki |
No minimum |
n/a |
Industrial |
No minimum |
n/a |
Controlled activity |
Restricted discretionary activity |
Discretionary activity |
---|---|---|
20 hectares. One small allotment (minimum area of 4000m²) provided there is at least a 20 hectare balance remaining. |
Up to three small allotments (minimum area of 4000m²) provided there is at least a 20 hectare balance remaining. |
Up to four small allotments (less than 20 hectares) provided there is at least a four hectare balance remaining. |
The number of allotments that can be applied for is calculated from the certificate of title as it existed on 5 March 1999. The balance area remaining must be from the Computer Freehold Register subject to the subdivision. |
Note: These sizes do not include the area required to provide access to rear allotments.
Generally, building consent applications can't be lodged until the new certificate of title has been issued.
Accepting building consent applications prior to this stage is problematic because infrastructure (such as water supply and waste disposal), earthworks, ground conditions and other requirements have not yet been finalised or conditions on subdivision consents have not been met.
However, we may accept a building consent application for land where the certificate of title hasn't been issued if certain information requirements are met. These requirements are outlined in the form above.
This requires a standard building consent.
The adopted Land Development and Subdivision Infrastructure Standard (Local Amendments Version 3) sets out the minimum standards of technical performance and quality for the subdivision and development of land and infrastructure.
Was this page useful?
Page last updated: 11:54pm Sun 30 June 2024