A fast-track resource consent is a normal resource consent that must be processed in 10 working days, rather than the normal 20 working days.
Currently this only applies to controlled land-use applications. These are ones that are non-notified and must be granted but can have conditions attached. Subdivisions cannot be fast-tracked.
Process
Use the normal land use application form (Form 9), there is now an added box to tick if you think your application could be fast-tracked.
Fee
The fees are the same as for a controlled land use resource consent applications.